01
Interprovincial oil pipeline, 75 km or more of new right of way
Threshold75 km or more of new right of way, CER-regulated
2 Sept 2026IAA panel
→
TodayCER Act
Moved Still a federal review. Different statute, different reviewer.
Federal review continues under the CER Act. The Governor in Council still makes the final call. What is gone is the integrated review panel — assessment by experts seated from outside the regulator.
See the regulation text →
02
Oil and gas pipeline through a national park
ThresholdCER-regulated facility in a national park or protected area
2 Sept 2026IAA panel
→
TodayCER Act
Moved Still a federal review. Different statute, different reviewer.
Named in the government's own list of removals. The park does not change the answer; CER regulation does.
See the regulation text →
03
International power line, 345 kV or more, 75 km or more of new right of way
Threshold345 kV or more and 75 km or more of new right of way
2 Sept 2026IAA panel
→
TodayCER Act
Moved Still a federal review. Different statute, different reviewer.
The entry and the defined term that scoped it were both removed in the same instrument.
See the regulation text →
04
Offshore renewable energy project regulated under the CER Act
ThresholdRegulated under the CER Act
2 Sept 2026IAA panel
→
TodayCER Act
Moved Still a federal review. Different statute, different reviewer.
For CER-regulated offshore renewables the CER is the final decision-maker, not the Governor in Council. The decision leaves Cabinet entirely.
See the regulation text →
05
New fossil-gas power plant, 200 MW or more
Threshold200 MW or more production capacity
2 Sept 2026IAA
→
TodayProvincial
Dropped No federal impact assessment. The province decides.
No federal impact assessment at any threshold. The province decides whether this project is assessed at all.
See the regulation text →
06
Fossil-gas plant expansion, +50% and 200 MW or more total
Threshold50% increase and 200 MW or more total
2 Sept 2026IAA
→
TodayProvincial
Dropped No federal impact assessment. The province decides.
Same answer as a new plant. Federal designation is gone.
See the regulation text →
07
New in situ oil sands facility, 2,000 m³/day or more
Threshold2,000 m³/day bitumen, in a province with no legislated oil sands emissions cap
2 Sept 2026IAA
→
TodayProvincial
Dropped No federal impact assessment. The province decides.
The old entry only bit where a province had no legislated cap on oil sands emissions, or had reached it. That conditional federal backstop is now gone.
See the regulation text →
08
In situ oil sands expansion, +50% and 2,000 m³/day or more
Threshold50% increase and 2,000 m³/day or more total
2 Sept 2026IAA
→
TodayProvincial
Dropped No federal impact assessment. The province decides.
Same conditional backstop, same repeal.
See the regulation text →
09
New hydroelectric dam, 200 MW or more
Threshold200 MW or more production capacity
2 Sept 2026IAA
→
TodayIAA
Unchanged Same pathway as before the amendment.
Nothing changed. A large dam is designated today exactly as it was before the amendment.
See the regulation text →
10
New nuclear waste storage or disposal facility
ThresholdNew storage, long-term management or disposal facility
2 Sept 2026IAA
→
TodayIAA
Unchanged Same pathway as before the amendment.
Nothing changed.
See the regulation text →